Aqua Metals Announces Continued Progress on Sierra ARC Buildout and Ongoing Efforts to Finance Remainder of Construction and Commissioning

Company continues to pursue financing for Sierra ARC through commissioning, impacted by further dips in battery minerals pricing;
Deploys cash preservation initiatives, and extends pilot operations to support continued strategic partner development

RENO, Nev., Aug. 05, 2024 (GLOBE NEWSWIRE) -- Aqua Metals, Inc. (NASDAQ: AQMS), a pioneer in sustainable lithium battery recycling, today provided an update on its progress and strategic initiatives. Development of its first commercial scale black mass recycling facility, the Sierra ARC, has progressed throughout Q2, including completion of a five megawatt upgrade of utility power, installation of switchgear, steel superstructures, equipment platform with two overhead cranes, as well as equipment deliveries, including tanks, evaporation systems, controls systems, and other key equipment.

To complete the Sierra ARC, the Company will need additional financing. In May 2024, Aqua Metals announced the signing of a non-binding term sheet with one of the world’s largest privately held companies for a secured credit facility of up to $33 million. However, the Company was recently advised by the lender that it was suspending further activity with regard to the secured credit facility due to continued high interest rates and recent declines in the market price for lithium-ion minerals, including an over 25% drop in lithium carbonate pricing, since signing the term sheet. These factors raised concerns on the part of the lender regarding the ability of Aqua Metals to meet the lender’s proposed debt service covenants. This follows two months of rigorous due diligence by the lender, which management believes satisfied the lender’s inquiries into the Company’s technology, processes, supply and offtake chain and overall effectiveness of the ability to recycle black mass. Management intends to maintain communications with the lender in the hopes of resuming negotiations in the event of declining interest rates and/or rising mineral prices. Simultaneously, management continues to actively pursue the required funding through various other engagements with funding counterparties, including debt, project finance, joint venture and strategic investment options.

The Company also announced that due to the delay in funding, it has completed a reduction in force of personnel hired largely in expectation of securing the required funding for the completion of the Sierra ARC and commencement of operations. The Company however does not expect the reduction in force to materially impact its current pilot operations or continuing research and development. Although the Sierra ARC continues to be at or under budget to date, attributable to both the benefits of piloting Li AquaRefining™ technology in 2022 and 2023 and the disciplined approach to procurement and build, the timeline is now shifting into 2025 compared to the previously planned late 2024 commissioning. Management believes that the reduction in force, coupled with non-essential asset disposition, deferral of certain expenses and more standard equipment leasing, will provide approximately one year of cash runway with no other sources of cash.

Second Quarter Highlights:

1.   Advancements at the Sierra ARC

The Sierra ARC facility has surpassed numerous milestones, including the completion of floor reinforcement, equipment foundations, electric utility and switchgear upgrades, and mezzanine installation with overhead cranes. We have begun receiving and installing the initial equipment, including tanks, chillers, evaporators, and controls with testing underway.

2.   Pilot Facility Operations

The pilot facility has been consistently operating 24x5, showcasing the scalability and efficiency of Aqua Metals' AquaRefining™ technology. We believe these operations provide critical process validation data as a part of due diligence conducted by financing counterparties.

3.   Successful Capital Raise

Aqua Metals completed a $7.3 million net funding round, reflecting continued investor confidence in the Company’s technology and business plan.

Looking Ahead

As Aqua Metals moves forward into the latter half of 2024, the Company is focused on achieving several strategic objectives:

  • Continued engagement with counterparties to finance the remainder of the Sierra ARC build in a way that does not require overburdened debt service. This includes project finance, strategic financial and/or industry investments.
  • Continued Equipment Provisioning at the Sierra ARC: Upon successful completion of the financing efforts, the Company is in a position to move quickly to complete the remaining mechanical, electrical, plumbing, process equipment installs within 2 to 3 quarters and commence commissioning and scaling.
  • Expanding Strategic Partnerships: Aqua Metals continues to explore and solidify partnerships that enhance its supply chain and expand its market presence. Collaborations with announced industry leaders like 6K Energy, Dragonfly Energy, and Yulho Materials as well as further developing unannounced partners are pivotal to the Company’s strategy.
  • Continued Pilot Operations: The Company intends to continue operations of its pilot facility at the Innovation Center and produce battery grade materials for existing and prospective industry partners. The Company believes that continued pilot operations will also serve as an ongoing operating showcase of low cost, decarbonized, sodium sulfate free, safe and clean working environment in contrast to smelting and other hydrometallurgical methods.

Conference Call and Webcast

The Company will hold a conference call to discuss results and corporate developments today at 4:30 p.m. ET. Investors can access the live conference call at https://event.webcasts.com/aqms or from the investor relations section of the Company’s website at https://ir.aquametals.com/. Alternatively, interested parties can access the audio call by dialing 877-407-9708 (toll-free) or 201-689-8259 (international).

Following the conclusion of the live event, a replay will be available by dialing 877-660-6853 or 201-612-7415 and using passcode 13748295. The webcast replay will also be available in the “News / Events” section of the Aqua Metals website.

About Aqua Metals

Aqua Metals, Inc. (NASDAQ: AQMS) is reinventing metals recycling with its patented AquaRefining™ technology. The Company is pioneering a sustainable recycling solution for materials strategic to energy storage and electric vehicle manufacturing supply chains. AquaRefining™ is a low-emissions, closed-loop recycling technology that replaces polluting furnaces and hazardous chemicals with electricity-powered electroplating to recover valuable metals and materials from spent batteries with higher purity, lower emissions, and minimal waste. Aqua Metals is based in Reno, NV and operates the first sustainable lithium battery recycling facility at the Company’s Innovation Center in the Tahoe-Reno Industrial Center. To learn more, please visit www.aquametals.com.

Aqua Metals Social Media

Aqua Metals has used, and intends to continue using, its investor relations website (https://ir.aquametals.com), in addition to its Twitter, Threads, LinkedIn and YouTube accounts at https://twitter.com/AquaMetalsInc (@AquaMetalsInc), https://www.threads.net/@aquametalsinc (@aquametalsinc), https://www.linkedin.com/company/aqua-metals-limited and https://www.youtube.com/@AquaMetals respectively, as means of disclosing material non-public information and for complying with its disclosure obligations under Regulation FD.

Safe Harbor

This press release contains forward-looking statements concerning Aqua Metals, Inc. Forward-looking statements include, but are not limited to, our plans, objectives, expectations and intentions and other statements that contain words such as "expects," "contemplates," "anticipates," "plans," "intends," "believes", "estimates", "potential" and variations of such words or similar expressions that convey the uncertainty of future events or outcomes, or that do not relate to historical matters. The forward-looking statements in this press release include our expectations for our pilot and commercial-scale recycling plants, our ability to recycle lithium-ion batteries and the expected benefits of recycling lithium-ion batteries. Those forward-looking statements involve known and unknown risks, uncertainties, and other factors that could cause actual results to differ materially. Among those factors are: (1) the risk that we may not be able to successfully negotiate and conclude a definitive license agreement with Yulho or a definitive pilot facility agreement with 6K, (2) even if we are to conclude definitive agreements with Yulho and/or 6K, the risk that we may not achieve the expected benefits from such relationships; (3) the risk that we may not be able to acquire the funding necessary to develop our recently acquired five-acre campus; (4) the risk that we may not be able to develop the recycling facility on the five-acre campus within the expected time or at all; (5) even if we are able to develop the recycling facility, the risk that we may not realize the expected benefits; (6) the risk that potential licensees may refuse or be slow to adopt our AquaRefining process as an alternative in spite of the perceived benefits of AquaRefining; (7) the risk that we may not realize the expected economic benefits from any licenses we may enter into; and (8) those risks disclosed in the section "Risk Factors" are included in our Annual Report on Form 10-K filed on March 28, 2024. Aqua Metals cautions readers not to place undue reliance on any forward-looking statements. The Company does not undertake and specifically disclaims any obligation to update or revise such statements to reflect new circumstances or unanticipated events as they occur, except as required by law.

Contact Information

Investor Relations
Bob Meyers & Rob Fink
FNK IR
646-878-9204
aqms@fnkir.com

Media
David Regan
Aqua Metals
775-446-5398
David.Regan@aquametals.com

Source: Aqua Metals

 
AQUA METALS, INC.
Condensed Consolidated Balance Sheets - Unaudited
(in thousands, except share and per share amounts)
             
    June 30, 2024     December 31, 2023  
ASSETS                
Current assets                
Cash and cash equivalents   $ 7,833     $ 16,522  
Note receivable - LINICO     400       600  
Accounts receivable           67  
Inventory     908       929  
Prepaid expenses and other current assets     174       181  
Total current assets     9,315       18,299  
                 
Non-current assets                
Property, plant and equipment, net     17,009       10,347  
Intellectual property, net     191       281  
Other assets     7,706       4,673  
Total non-current assets     24,906       15,301  
                 
Total assets   $ 34,221     $ 33,600  
                 
LIABILITIES AND STOCKHOLDERS’ EQUITY                
                 
Current liabilities                
Accounts payable   $ 1,679     $ 1,836  
Accrued expenses     2,908       2,467  
Lease liability, current portion     288       275  
Note payable, current portion     2,979       35  
Total current liabilities     7,854       4,613  
                 
Non-current liabilities                
Lease liability, non-current portion     593        
Note payable, non-current portion           2,923  
Total liabilities     8,447       7,536  
                 
Commitments and contingencies (see Note 12)                
                 
Stockholders’ equity                
Common stock; $0.001 par value; 300,000,000 shares authorized; 134,257,193 and 133,800,547, shares issued and outstanding as of June 30, 2024, respectively and 108,308,661 and 107,880,095, shares issued and outstanding as of December 31, 2023, respectively     134       108  
Additional paid-in capital     260,554       249,687  
Accumulated deficit     (234,554 )     (223,215 )
Treasury stock, at cost; common shares: 456,646 and 428,566 as of June 30, 2024 and December 31, 2023, respectively     (360 )     (516 )
Total stockholders’ equity     25,774       26,064  
                 
Total liabilities and stockholders’ equity   $ 34,221     $ 33,600  
                 


 
AQUA METALS, INC.
Condensed Consolidated Statements of Operations - Unaudited
(in thousands, except share and per share amounts)
             
    Three Months Ended June 30,     Six Months Ended June 30,  
    2024     2023     2024     2023  
                                 
Operating cost and expense                                
Plant operations   $ 2,373     $ 1,481     $ 4,582     $ 2,546  
Research and development cost     363       525       951       970  
Gain on disposal of property, plant and equipment           (3 )           (23 )
General and administrative expense     2,863       2,849       5,858       5,855  
Total operating expense     5,599       4,852       11,391       9,348  
                                 
Loss from operations     (5,599 )     (4,852 )     (11,391 )     (9,348 )
                                 
Other income and (expense)                                
Interest expense     (84 )     (255 )     (190 )     (431 )
Interest and other income     99       348       245       414  
                                 
Total other income (expense), net     15       93       55       (17 )
                                 
Loss before income tax expense     (5,584 )     (4,759 )     (11,336 )     (9,365 )
                                 
Income tax expense     3             3        
                                 
Net loss   $ (5,587 )   $ (4,759 )   $ (11,339 )   $ (9,365 )
                                 
Weighted average shares outstanding, basic and diluted     123,793,140       84,184,884       116,923,889       82,743,345  
                                 
Basic and diluted net loss per share   $ (0.05 )   $ (0.06 )   $ (0.10 )   $ (0.11 )
                                 